Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC)Residential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Waterline Installation and Sewer Work on Western Avenue Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC)…Continue Reading Week of October 28, 2024

Week of October 28, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of October 28. Please note that items in BOLD are expected to generate some noticeable noise. Dates 10/28/24 to 11/2/24: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of October 28, 2024