Week of December 2, 2024

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

  • Thermal striping in the Harvard Business School lot will take place next spring.
  • Contractors are pulling cable through manholes along the route from the District Energy Facility (DEF) to Kresge Way.  Next week crews will be testing at designated manholes Monday through Wednesday.

Enterprise Research Campus (ERC)

Residential/Hotel

  • On Saturday, November 30, a large crane will be set up on Trotting Avenue to load mechanical equipment onto the roof of the hotel. This activity will begin with parts of the crane arriving at 6 a.m. and continuing to 6 p.m.  Dismantling of the crane may go until 8 p.m. Roofing activities and miscellaneous interior work will take place.
  • The high-rise building has topped off at level 18.
  • The mid-rise residential building has topped off at their mechanical penthouse at level 9.
  • Windows, exterior sheathing, framing and waterproofing are being installed on the residential buildings.
  • Exterior panel installation is ongoing at the hotel.
  • A suspended scaffolding deck like under a bridge is set up on the underside of the cantilever section at the hotel.
  • Elevators are being installed.
  • Other smaller concrete operations continue.
  • Roofing activities are underway.
  • MEP work is ongoing.
  • Framing is taking place in certain areas of the building.
  • Temporary heaters are being set up.

Laboratory and Office Buildings.

  • The west tower crane will be dismantled and removed from site beginning next Friday into the weekend requiring after hours work. This work is weather dependent.
    • The arrival and assembly of a large crane with another assist crane will begin at 5:30 a.m. on Friday, November 29.  Trucks will be arriving on site to begin removing tower crane parts at noon. Crews will work until 6 p.m.
    • On Saturday, November 30, starting at 6 a.m. to 6 p.m. crews will continue to dismantle the crane with approximately 18 truckloads of crane parts will be removed from the site, entering and exiting at both the Hague Street and Milestone Street gates.
    • On Sunday, December 1, starting at 6 a.m. to 6 p.m. finishing the tower crane removal activities including disassembly and removal of the large crane and its assist crane.
  • On Saturday, November 30, miscellaneous mechanical work on the penthouse and general cleanup will also be underway.
  • State police-escorted oversize trucks will deliver air handlers on Wednesday, December 4, Thursday, December 5 and Friday, December 6 at 5 a.m. The tower crane will be used to unload the trucks after 7 a.m.  
  • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
  • Exterior curtain-wall panels are being installed during the week.
  • Smaller concrete operations continue.
  • Both east and west buildings structural steel have topped off. 
  • Roof activities are underway. 
  • Spray-on fireproofing continues.
  • MEP work is ongoing.
  • Masonry work continues.
  • Temporary heaters are being set up.

Greenway

  • Drainage structures and pipe installation are underway.
  • Concrete activity for the rainwater storage tank will continue.
  • Backfilling continues.
  • Bulk excavation is complete. 

Treehouse Conference Center

  • Mass timber activities will take place on Saturday, November 30. A crane will be in operation.
  • Mass timber deliveries and installation on the third floor deck continue with a crane operating during the week.
  • MEP activities and miscellaneous utilities are ongoing. 

Waterline Installation and Sewer Work on Western Avenue

  • Relocation of the fence line back closer to Western Avenue has begun with line striping to follow on either Friday or Tuesday nights, November 29 or December 3.

Building Mock-Ups

  • Building mockups are on the corner of Hague and Rotterdam Streets.

Eversource Conduit Project

  • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. This public utility work is not under the supervision of ERC.

General

  • The project’s work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
  • Saturday work is scheduled to take place starting at 7 a.m.
  • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
  • Intermittent use of power trowels for concrete finishing and layout for concrete placement may take place after 6 p.m.
  • Drones will be in use bi-weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Weekly flights are weather dependent and are scheduled one weekday morning.
    • Drones will be flying at 8 a.m. on Thursday, December 5. 

North Allston Storm Drain Extension Project (NASDEP)
The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the inundated existing storm water systems in North Allston, continues with enabling work on the ERC site.

  • Maintaining the site with a water truck and sweeper weekly.
  • Installing temporary poles at the DPY.

92 Seattle Street
Renovation for reuse of this Harvard building is complete and some final punch list items will be completed during winter break.

175 North Harvard Street, 100 South Campus Drive 

The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):

  • The structural steel phase of the housing project is ongoing with work finishing on levels 10 and 11 soon with levels 12 and 13 to follow. Steel should be completed later in December with a topping off tentatively scheduled for December 18. Decking and detailing will continue through December. Concrete pours will continue this week. Mechanical, electrical, and plumbing trades continue to work throughout the site. A subcontractor continues working on small utilities, including storm, duct bank, and data and is backfilling around the foundation. Exterior waterproofing continues and crews are fireproofing on several levels. This work will continue progressing up the building. The dewatering tank will be removed at the end of December.
  • The temporary construction hoist (exterior elevator) tower installation is underway closer to South Campus Drive and is expected to be operational by the second week of December. Steel stairways are being placed.
  • Within the next couple of weeks, the building’s exterior will be enclosed with tarping to retain temporary heat. Temporary heaters are being installed.
  • Neighbors will continue to see road closures on South Campus Drive in support of concrete operations to allow for concrete pump placement and site access. All pours are anticipated to take place on weekdays during normal working hours with the road being returned at the end of each day. Signage and details will be provided to divert traffic as needed.
  • Concrete deck placements can be expected each week from level 8 to the roof level during regular work hours into December – some finishing work may extend beyond 6 p.m. depending on weather conditions. A pump truck will be present on South Campus Drive during concrete pours.
  • Within the next six to eight weeks, work will begin taking place at the roof level. Personnel on upper floors and exterior staging will continue yet should be less noticeable in the coming months when the exterior building wrap is in place.
  • The tower crane will be in use for the next two months during normal working hours and is placed in weathervane mode with safety lighting turned inward at the end of every shift.
  • Wheel washing and street sweeping continues to ensure soil is not being tracked through the neighborhood streets.
  • On the new American Repertory Theater (ART) work site, a mix of backfilling, and interior and exterior concrete wall and pier placements continues. Excavation for loading dock foundations is underway. Interior slab and exterior wall waterproofing is ongoing. Utility installation around the perimeter of the building continues.
  • Structural steel will be arriving on the ART site on Monday, December 9, and installation will run through January. A crane will be set up on site that morning to support this work. Multiple concrete placements to enable structural steel installation will take place each week for the next few weeks. There is potential for early work starts and late finishes during some of these placements. Installation will run through mid-December and detailing through January.
  • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will follow in February.
  • Work continues on the building mock-ups to review design and constructability across North Harvard Street. At the ART mockup, activities will take place intermittently. Adjustments continue intermittently on the housing mockup to include framing, sheathing, and masonry.
  • Both job sites will be open, and crews will be working on Friday, November 29.
  • Crews at the affiliate housing building site will be working on Saturday, November 30. A crane will be on site on Saturday to install precast stairs. Crews at the ART project will also be working on Saturday, November 30, on concrete preparation and foundation wall forms from 7 a.m. to 4 p.m.
  • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.

210 North Harvard Street

  • Eversource or Verizon will remove an old pole and power line.
  • The bakery Sofra is now open. 

168 Western Ave

  • Shawmut continues interior work and is coordinating with the Swiss Bakers operation.
  • Exterior work stopped and will pick up again on January 8 for a month.

304 Western Ave

  • The roofing project will be completed this week.

55 Antwerp St

  • Sidewalk and fence work remobilized on November 26.
  • The fence will be substantially complete by December 6.

Soldiers Field Garage Masonry Repairs and Office HVAC Replacement

  • The project demobilized on November 25.