The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 18. Please note that items in BOLD are expected to generate some noticeable noise.Dates 11/18/24 to 11/23/24: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of November 18, 2024
Week of November 18, 2024
175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at thefuture location of the new Harvard University affiliate housing building and American Repertory Theatre(ART):…Continue Reading Week of November 18, 2024
Week of November 11, 2024
All sites will not be working on Veterans Day, Monday, November 11, 2024. Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC)Residential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Waterline Installation and Sewer Work on Western Avenue Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension…Continue Reading Week of November 11, 2024
Week of November 11, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 11. Please note that items in BOLD are expected to generate some noticeable noise. Dates 11/11/24 – 11/09/24PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of November 11, 2024
Week of November 11, 2024
175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at thefuture location of the new Harvard University affiliate housing building and American Repertory Theatre(ART):…Continue Reading Week of November 11, 2024
Week of November 11, 2024
The following summarizes the utility work planned in the Littauer Lot for the week of November 11. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 11/12/24-11/15/24 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of November 11, 2024
Allston Development Monthly Update November 2024
Enterprise Research Campus Phase A Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update November 2024
Week of November 4, 2024
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC)Residential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Waterline Installation and Sewer Work on Western Avenue Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC)…Continue Reading Week of November 4, 2024
Week of November 4, 2024
PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of November 4, 2024
Week of November 4, 2024
175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at thefuture location of the new Harvard University affiliate housing building and American Repertory Theatre(ART):…Continue Reading Week of November 4, 2024