The following summarizes the utility work planned in the Littauer Lot for the week of December 9. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 12/9/24-12/13/24 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of December 9, 2024
Week of December 9, 2024
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) Residential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Waterline Installation and Sewer Work on Western Avenue Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project…Continue Reading Week of December 9, 2024
Week of December 9, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 9. Please note that items in BOLD are expected to generate some noticeable noise. Dates 12/9/24 to 12/14/24: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of December 9, 2024