The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 24. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 24, 2024
Week of June 17, 2024
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot Expansion Construction has begun on the new American Repertory Theater (ART), which will be located at the front of the 175 North Harvard parcel with the new Harvard…Continue Reading Week of June 17, 2024
Week of June 17, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 17. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 17, 2024
Week of June 10, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 10. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 10, 2024
Week of June 10, 2024
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot ExpansionConstruction has begun on the new American Repertory Theater (ART), which will be located at the front of the 175 North Harvard parcel with the new Harvard University…Continue Reading Week of June 10, 2024
Allston Development Monthly Update- June 2024
Enterprise Research Campus Phase A Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update- June 2024
Week of June 3, 2024
The Western Avenue utility crossing roadway and Kresge Way phase of infrastructure work is finishing up with inspections and punch list work in coordination with University operations. Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot…Continue Reading Week of June 3, 2024
Week of June 3, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 3. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 3, 2024
Week of May 27, 2024
All sites will not be working on Memorial Day, Monday, May 27, 2024. The Western Avenue utility crossing roadway and Kresge Way phase of infrastructure work is finishing up with inspections and punch list work in coordination with University operations. Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle…Continue Reading Week of May 27, 2024
Week of May 27, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 27. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of May 27, 2024