The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 19. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS:• Continuous deliveries and dumpster swaps will occur throughout the week.• Water Service work will continue next week. Work will continue…Continue Reading Week of August 19, 2024
Week of August 12, 2024
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Overhead mast arm lights will be installed after delivery and thermal striping in the Harvard Business School lot will take place this fall. Enterprise Research Campus (ERC) Residential/Hotel Laboratory and Office Buildings Greenway Treehouse Conference Center Building Mock-Ups General •The site’s four tower cranes…Continue Reading Week of August 12, 2024
Week of August 12, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 12. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of August 12, 2024
Week of August 12, 2024
175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at thefuture location of the new Harvard University affiliate housing building and American Repertory Theatre(ART):…Continue Reading Week of August 12, 2024
Week of August 5, 2024
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) Residential/Hotel Laboratory and Office Buildings Greenway Treehouse Conference Center Building Mock-Ups General Next flight is scheduled for Friday, August 2 at 11 a.m 92 Seattle Street 175 North Harvard Street, 100 South Campus Drive Construction is underway on the new…Continue Reading Week of August 5, 2024
Week of August 5, 2024
The following summarizes the work planned on the Eliot and Kirkland Exploratory Summer 2024 Project. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of August 5, 2024
Allston Development Monthly Update- August 2024
Enterprise Research Campus Phase A Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update- August 2024
Week of August 5, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 5. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS:• Continuous deliveries and dumpster swaps throughout the week.• Water Service work will begin next week on Monday 8/5. Work will…Continue Reading Week of August 5, 2024
Week of August 5, 2024
175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at thefuture location of the new Harvard University affiliate housing building and American Repertory Theatre(ART):…Continue Reading Week of August 5, 2024
Week of July 29, 2024
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Overhead mast arm lights will be installed and thermal striping in the Harvard Business School lot will take place this summer. Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot Expansion Construction is underway on…Continue Reading Week of July 29, 2024