The following summarizes the work planned for the new FAS building for the week of November 3, 2025: Dates: 11/3/25 – 11/7/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of November 3, 2025
Week of October 27, 2025
Enterprise Research Campus Residential/Hotel Weekend Activities Weekday/Night Activities Laboratory and Office Buildings Weekend Activities Weekday Activities Treehouse Conference Center Weekend Activities Weekday/Night Activities Greenway Weekend Activities Weekday Activities Streetscape and Western Avenue Weekend Activities Weekday/night Activities ERC Balance 1.4 Building Mock-ups General North Allston Storm Drain Extension Project (NASDEP) The NASDEP, a project designed for…Continue Reading Week of October 27, 2025
Week of October 27, 2025
GENERAL OCCUPANT INFORMATION PLAZA WORK: Week of 10/27/25 IMPACTS– high noise level from chipping, cutting and grinding will be most noticeable north of the building footprint as well as near Kirkland Street. INTERIOR WORK: Week of 10/27/25 IMPACTS- medium noise level from cutting, chipping and grinding…Continue Reading Week of October 27, 2025
Week of October 27, 2025
175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of October 27, 2025
Week of October 27, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, October 27, 2025: Dates: 10/27/25 – 10/31/25 KIRKLAND HOUSE IMPACTS: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: 10/25/25 WORK HOURS:…Continue Reading Week of October 27, 2025
Week of October 27, 2025
The following summarizes the work planned for the new FAS building for the week of October 27, 2025: Dates: 10/27/25 – 10/31/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of October 27, 2025
Week of October 20, 2025
Enterprise Research Campus Residential/Hotel Weekend Activities Weekday/Night Activities Laboratory and Office Buildings Weekend Activities Weekday Activities Treehouse Conference Center Weekend Activities Weekday/Night Activities Greenway Weekend Activities Weekday Activities Streetscape and Western Avenue Weekend Activities Weekday/night Activities ERC Balance 1.4 Building Mock-Ups General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston…Continue Reading Week of October 20, 2025
Week of October 20, 2025
The following summarizes the work planned at 12 Palmer St for the week of October 20. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/20/25 – 10/24/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.• There will be a crane pick on Wednesday 10/22. This will…Continue Reading Week of October 20, 2025
Week of October 20, 2025
175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of October 20, 2025
Week of October 20, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, October 20, 2025: Dates: 10/20/25 – 10/26/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: KIRKLAND HOUSE IMPACTS: WORK HOURS:…Continue Reading Week of October 20, 2025