Year: 2025

Week of August 11, 2025

General Project Information Exterior Plaza Work Scheduled for week of 8/11/2025 Expected Impacts – high noise levels from chipping, cutting, and grinding will be most noticeable in areas west of the building footprint. Interior Work Scheduled for week of 8/11/2025 Expected Impacts – high noise level from cutting, chipping and grinding….Continue Reading Week of August 11, 2025

Week of August 4, 2025

General Project Information Exterior Plaza Work Scheduled for week of 8/4/2025 Expected Impacts – high noise level from chipping, cutting and grinding will be most noticeable in areas west of the building footprint. Interior Work Scheduled for week of 8/4/2025 Expected Impacts – high noise level from cutting, chipping and grinding….Continue Reading Week of August 4, 2025

Week of August 11, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities Weekday/Night Activities GreenwayWeekend Activities Weekday Activities Streetscape and Western AvenueWeekend Activities Weekday Activities Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP,…Continue Reading Week of August 11, 2025

Allston Development Monthly Update July 2025

Enterprise Research Campus Phase A  Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update July 2025

Week of August 4, 2025

The following summarizes the work planned at 12 Palmer St for the week of August 4. Please note that items in BOLD are expected to generate some noticeable impacts.  Week of: 8/4/25 – 8/8/25 Temporary Public Way Impacts: • Tuesday 8/5 concrete pour. Pump truck will arrive at 7am and setup in front of our main gate, concrete…Continue Reading Week of August 4, 2025