Year: 2025

Week of March 3, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate…Continue Reading Week of March 3, 2025

Week of March 3, 2025

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of March 3. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 03/03/25-03/08/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of March 3, 2025

Week of February 18, 2025

Starting next week, Tuesday, February 18, neighbors will observe the contractor setting up a temporary tent structure on the west side of the William James Hall Plaza.  Project materials will continue to be delivered by way of Divinity Ave with truck traffic to the site expected to increase beginning next week as well. Project Schedule …Continue Reading Week of February 18, 2025

Week of January 6, 2025

William James Hall Plaza Renovation Work Begins on January 6, 2024 As part of the Harvard University’s Faculty of Arts and Sciences campus construction activities, contractors are set to commence a multi-phase renovation project of the plaza that surrounds William James Hall at 33 Kirkland Street. Early mobilization will take place in late December including…Continue Reading Week of January 6, 2025

Week of February 24, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate…Continue Reading Week of February 24, 2025

Week of February 24, 2025

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 24. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 2/24/25-3/1/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of February 24, 2025