GENERAL OCCUPANT INFORMATION PLAZA WORK: Week of 10/6/25 IMPACTS- high noise level from chipping, cutting and grinding will be most noticeable in the north of building footprint. A vacuum truck will produce elevated noise levels. INTERIOR WORK: Week of 10/6/25 IMPACTS- medium noise level from cutting, chipping and grinding…Continue Reading Week of October 6, 2025
Week of October 6, 2025
The following summarizes the work planned at 12 Palmer St for the week of October 6. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/6/25 – 10/10/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street. Exterior Site Activities:• Masons will be demoing brick above 32-42 Church Street which…Continue Reading Week of October 6, 2025
Week of October 6, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus Residential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities Weekday/Night Activities GreenwayWeekend ActivitiesOn Saturday, October 4, pavers will be installed and planting activity will be underway.Weekday Activities Streetscape and Western AvenueWeekend Activities Weekday/night Activities ERC…Continue Reading Week of October 6, 2025
Week of October 6, 2025
The following summarizes the work planned for the new FAS building for the week of October 6, 2025: Dates: 10/6/25 – 10/10/25 PUBLIC WAY IMPACTS EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of October 6, 2025
Week of September 29, 2025
GENERAL OCCUPANT INFORMATION PLAZA WORK: Week of 9/29/2025 IMPACTS– high noise levels from chipping, cutting and grinding will be most noticeable north of building footprint. A vacuum truck will produce elevated noise levels. INTERIOR WORK: Week of 9/29/2025 IMPACTS- medium noise levels from cutting, chipping and grinding…Continue Reading Week of September 29, 2025
Week of September 29, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus Residential/Hotel Weekend Activities Weekday/Night Activities Laboratory and Office Buildings Weekend Activities Weekday Activities Treehouse Conference Center Weekend Activities Weekday/Night Activities Greenway Weekend ActivitiesOn Saturday, September 27, masons will be working on the footing forms at the bio-swale area. Weekday Activities Streetscape…Continue Reading Week of September 29, 2025
Week of September 29, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, September 29, 2025: Dates: 09/29/25 – 10/05/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of September 29, 2025
Week of September 29, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 29. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/29/25 – 10/3/25 Temporary Public Way Impacts: Exterior Site Activities: Other Impacts: Work Hours:…Continue Reading Week of September 29, 2025
Week of September 29, 2025
The following summarizes the work planned for the new FAS building for the week of September 29, 2025: Dates: 9/29/25 – 10/3/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of September 29, 2025
Adams House Final Notice
Dear Neighbors: As part of Harvard House Renewal’s multi-phase renovation of Adams House, work on Russell Hall, Library Commons, and Westmorly Court at 26 Plympton/13-21 Bow Street is now substantially complete. As a reminder, the project’s scope was exterior restoration of the buildings, including new roofs, rebuilding chimneys, dormers, and repointing the brick facade, and…Continue Reading Adams House Final Notice