General Project Information Exterior Plaza Work Scheduled for week of 8/11/2025 Expected Impacts – high noise levels from chipping, cutting, and grinding will be most noticeable in areas west of the building footprint. Interior Work Scheduled for week of 8/11/2025 Expected Impacts – high noise level from cutting, chipping and grinding….Continue Reading Week of August 11, 2025
Week of August 4, 2025
General Project Information Exterior Plaza Work Scheduled for week of 8/4/2025 Expected Impacts – high noise level from chipping, cutting and grinding will be most noticeable in areas west of the building footprint. Interior Work Scheduled for week of 8/4/2025 Expected Impacts – high noise level from cutting, chipping and grinding….Continue Reading Week of August 4, 2025
Week of August 18, 2025
The following summarizes the work planned for the new FAS building for the week of August 18, 2025: Dates: 8/18/25-8/22/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of August 18, 2025
Week of August 11, 2025
The following summarizes the work planned at 12 Palmer St for the week of August 11. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 8/11/25 – 8/15/25Public Way Impacts:• Palmer Street will have a temporary road closure on Tuesday, 8/12/25, from 7 am – 2 pm for a crane pick….Continue Reading Week of August 11, 2025
Week of August 11, 2025
he following summarizes the work planned at Eliot House during the week beginning Monday, August 11, 2025: Dates: 08/11/25-08/17/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of August 11, 2025
Week of August 11, 2025
175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of August 11, 2025
Week of August 11, 2025
The following summarizes the work planned for the new FAS building for the week of August 11, 2025: Dates: 8/11/25-8/15/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of August 11, 2025
Week of August 11, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities Weekday/Night Activities GreenwayWeekend Activities Weekday Activities Streetscape and Western AvenueWeekend Activities Weekday Activities Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP,…Continue Reading Week of August 11, 2025
Allston Development Monthly Update July 2025
Enterprise Research Campus Phase A Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update July 2025
Week of August 4, 2025
The following summarizes the work planned at 12 Palmer St for the week of August 4. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 8/4/25 – 8/8/25 Temporary Public Way Impacts: • Tuesday 8/5 concrete pour. Pump truck will arrive at 7am and setup in front of our main gate, concrete…Continue Reading Week of August 4, 2025