GENERAL OCCUPANT INFORMATION 1. Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM 2. The plaza renovation project is targeting an end of May 2026 completion date. 3. The…Continue Reading Week of December 22, 2025
Weeks of December 22, 29, 2025 and January 9, 2026
175 North Harvard Street Project ConstructionThe following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Weeks of December 22, 29, 2025 and January 9, 2026
Weeks of December 22, 29 2025, and January 9, 2026
Construction Impacts Update Weeks of December 22 and 29, 2025 and January 5, 2026 DEF Extension into Harvard Business School Enterprise Research Campus Residential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities in Coordination with Treehouse Operation Weekday Activities in Coordination with Treehouse Operation GreenwayWeekend Activities Weekday Activities Streetscape…Continue Reading Weeks of December 22, 29 2025, and January 9, 2026
Week of December 22, 2025
Dates: 12/22/25-12/26/25 KIRKLAND HOUSE IMPACTS: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of December 22, 2025
Week of December 22, 2025
The following summarizes the work planned at 12 Palmer St for the week of December 22. Please note that items in BOLD are expected to generate some noticeable impacts. Week Of: 12/22/25 – 12/26/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of December 22, 2025
Week of December 22, 2025
The following summarizes the work planned for the new FAS building for the week of December 22, 2025: Dates: 12/22/25 – 12/26/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of December 22, 2025
Week of December 15, 2025
The following summarizes the work planned for the new FAS building for the week of December 15, 2025: Dates: 12/15/25 – 12/19/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of December 15, 2025
Week of December 15, 2025
The following summarizes the work planned at 12 Palmer St for the week of December 15. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 12/15/25 – 12/19/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of December 15, 2025
Week of December 15, 2025
Enterprise Research CampusResidential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities in Coordination with Treehouse Operations Weekday Activities in Coordination with Treehouse Operations GreenwayWeekend Activities Weekday Activities Streetscape and Western AvenueWeekend Activities Weekday/night Activities ERC Balance 1.4 Streetscape Building Mock-Ups General North Allston Storm Drain Extension Project (NASDEP)The NASDEP,…Continue Reading Week of December 15, 2025
Week of December 15, 2025
GENERAL OCCUPANT INFORMATION 1. Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM. 2. The plaza renovation project is targeting a summer 2026 completion date. 3. The front entrance…Continue Reading Week of December 15, 2025