Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus Residential/Hotel Laboratory and Office Buildings Greenway Treehouse Conference Center Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP) The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC)…Continue Reading Week of February 3, 2025
Week of February 3, 2025
Dates: 2/3/25-2/8/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of February 3, 2025
Week of January 27, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Building Mock-UpsBuilding mockups are on the corner of Hague and Rotterdam Streets.Eversource Conduit ProjectEversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to…Continue Reading Week of January 27, 2025
Week of January 27, 2025
Consigli/Bond are now planning to work on Saturday, January 25 from 9:00 AM to 4:00 PM. Dates: 1/27/25-1/31/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of January 27, 2025
Week of January 27, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 27. Please note that items in BOLD are expected to generate some noticeable noise. Dates 1/27/25 to 2/01/25:PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of January 27, 2025
Week of January 20, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate…Continue Reading Week of January 20, 2025
Week of January 20, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 20. Please note that items in BOLD are expected to generate some noticeable noise. Dates 1/20/25 to 1/25/25: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of January 20, 2025
Week of January 20, 2025
The following summarizes the utility work planned in the Littauer Lot for the week of January 20 Please note that items in BOLD are expected to generate some noticeable noise. Dates: 1/20/25-1/24/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of January 20, 2025
Week of January 13, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate…Continue Reading Week of January 13, 2025
Week of January 13, 2025
The following summarizes the utility work planned in the Littauer Lot for the week of January 13 Please note that items in BOLD are expected to generate some noticeable noise….Continue Reading Week of January 13, 2025