Week of January 6, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

  • Thermal striping in the Harvard Business School lot will take place next spring.
  • Contractors are finishing testing at manholes along the route from the District Energy Facility (DEF) to Kresge Way. 

Enterprise Research Campus

Residential/Hotel

  • On Saturday, January 4, boom lifts will be set up on Trotting Avenue, south side of the midrise and up on podium deck with exterior wall and roofing activity underway. Miscellaneous interior work with hoists operational is planned.
  • Windows and panels are also being installed during the week on the residential buildings.
  • Exterior panel and window installation are ongoing at the hotel.
  • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
  • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
  • Elevators are being installed.
  • Other smaller concrete operations continue.
  • Roofing activities are underway.
  • MEP work is ongoing.
  • Framing is taking place inside the buildings.
  • Temporary heaters are operating.

Laboratory and Office Buildings.

  • On Saturday, January 4, curtain-wall panels will be installed using the tower crane on the east building. A drywall delivery will take place, roofing, miscellaneous interior work and general cleanup will be underway.
  • Exterior curtain-wall panels are being installed during the week.
  • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
  • Smaller concrete operations continue.
  • Roof activities are underway.
  • MEP work is ongoing.
  • Mechanical penthouse activities continue.
  • Masonry work continues.
  • Temporary heaters are operational.

Greenway

  • Drainage, recharge system and pipe installation are underway.
  • Backfilling continues.

Treehouse Conference Center

  • Mass timber activities will take place on Saturday, January 4. A crane will be in operation.
  • Mass timber deliveries, activities and installation of the roof continue with a crane operating during the week.
  • Façade frame installation will begin using boom lifts.
  • MEP activities are ongoing. 

Building Mock-Ups

  • Building mockups are on the corner of Hague and Rotterdam Streets.

Eversource Conduit Project

  • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. This public utility work is not under the supervision of ERC.

General

  • Snow and ice removal and cleanup will take place as needed.
  • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
  • Saturday work is scheduled to take place starting at 7 a.m.
  • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
  • Drones will be in use bi-weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Weekly flights are weather dependent and are scheduled one weekday morning.
    • A drone is scheduled to fly Thursday, January 9 from 7 a.m. to 9 a.m.

Signage Project at SEC and Stadium Way

  • A signage installation project in front of the SEC building will be finishing up.
  • Barriers surround the work area.

North Allston Storm Drain Extension Project (NASDEP)
The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the inundated existing storm water systems in North Allston, continues with enabling work on the ERC site.

  • South of Science work between Rena Path and Rotterdam Street will continue this week.
  • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
  • Three weeks of excavation work for preclearing will begin on Thursday, January 9.

92 Seattle Street

  • Renovation for reuse of this Harvard building is complete and some final punch list items will be completed during winter break.
  • Tenants have been asked to relocate for the punch list work.  
  • Crews will be working inside the building on Saturday, January 4.
  • Harvard Capital Projects will make adjustments to tenant spaces starting on January 8.  

175 North Harvard Street, 100 South Campus Drive 
The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).

  • The structural steel phase of the housing project is finishing on upper levels, and the final steel delivery took place last week. Steel decking installation and detailing continues. Concrete deck placements will continue on upper levels to the roof and should be complete later in January. Mechanical, electrical, and plumbing trades are working throughout the site. Work continues working on small utilities, including storm, duct bank, and data and is backfilling around the foundation. Crews are fireproofing on several levels. This work will continue progressing up the building.
  • Crews began using the temporary construction hoist (exterior elevator) on Thursday, December 19. The height of the hoist will need to be increased in the coming weeks.
  • Installation of building wrap to retain temporary heat on upper floors during concrete and fireproofing activities is ongoing. A small amount of noise associated with the temporary heaters falls within normal limits and may be heard off-hours. Some tarping will be removed at the lower floors after the fireproofing is complete.
  • PLEASE NOTE: For the next several weeks, a combination of activities at both the new affiliate housing building and American Repertory Theatre (ART) projects will require the closure of South Campus Drive to all vehicles Monday through Friday from 7 a.m. to 5 p.m. All traffic leaving the Continuum and Trader Joe’s parking will be instructed to make a right turn only out of the garage. The road will be open to traffic each day after 5 p.m. and on weekends. Signage and details will be provided to divert traffic as needed and police details will be on site to provide assistance.
  • Concrete deck placements continue on the upper levels to the roof level during regular work hours throughout this month – some finishing work will extend beyond 9 p.m. with the colder temperatures. Noise is generated by the power trowels used for finishing. The fresh concrete needs to be covered with blankets for warmth while curing. A pump truck will be present on South Campus Drive during concrete pours.
  • The tower crane will be in use for the next month during normal working hours and is placed in weathervane mode with safety lighting turned inward at the end of every shift. The crane is scheduled to be disassembled and removed from the site over the weekend of February 1 and 2. Because this is a sizeable undertaking, the crane removal will require some after-hours work. More detail will be provided as the date gets closer.
  • Wheel washing and street sweeping continues to ensure soil is not being tracked through the neighborhood streets.
  • On the new American Repertory Theater (ART) work site, interior concrete walls and piers will continue after this through the first week of January. Exterior wall waterproofing is ongoing. Backfilling for exterior walls and excavating for utilities continues. Utility work continues around the building perimeter. Structural steel work at the ART site was finished during the week of December 30. Steel detailing for the theatre’s stage and fly tower structure and concrete placements will run through January.
  • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will follow in late February. A crane to support this work will mobilize on Friday, February 14.
  • Work continues on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for flashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently.
  • Crews at the affiliate housing building site will be working on Saturday, January 4, to continue installing structural steel. Heaters will be maintained by workers on Sundays through the winter.
  • Off hours snow and ice removal are expected as needed.
  • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.

210 North Harvard Street

  • Eversource or Verizon will remove an old pole and power line.
  • The bakery Sofra is open. 

168 Western Ave

  • Crews will begin excavation for preclearing soil inside the site related to a sanitary line on Tuesday, January 7.
  • Interior work continues and is coordinating with the Swiss Bakers operation.