Day: January 17, 2025

Week of January 20, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/Hotel Laboratory and Office Buildings. Greenway Treehouse Conference Center Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate…Continue Reading Week of January 20, 2025

Week of January 20, 2025

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 20. Please note that items in BOLD are expected to generate some noticeable noise. Dates 1/20/25 to 1/25/25: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of January 20, 2025