175 North Harvard Street, 100 South Campus Drive The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART)….Continue Reading Week of March 31, 2025
Week of March 31, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Utility Investigation at HBS Enterprise Research CampusResidential/HotelWeekend Activities Weekday Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities GreenwayWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities Weekday Activities Sewer Work on Western Ave. Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium…Continue Reading Week of March 31, 2025
Week of March 31, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of March 31. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 3/31/25-4/05/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of March 31, 2025
Week of March 31, 2025
The following summarizes the utility work planned in the Littauer Lot for the week of March 31. Please note that items in BOLD are expected to generate some noticeable noise Dates: 3/31/25-4/4/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of March 31, 2025
Week of March 24, 2025
175 North Harvard Street, 100 South Campus Drive The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART)….Continue Reading Week of March 24, 2025
Week of March 24, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of March 24. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 3/24/25-3/29/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of March 24, 2025
Week of March 24, 2025
The following summarizes the utility work planned in the Littauer Lot for the week of March 24. Please note that items in BOLD are expected to generate some noticeable noise Dates: 3/24/25-3/28/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS WORK HOURS:…Continue Reading Week of March 24, 2025
Week of March 24, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Utility Investigation at HBS Enterprise Research CampusResidential/HotelWeekend Activities Weekday Activities Laboratory and Office Buildings.Weekend Activities Weekday Activities Greenway Treehouse Conference CenterWeekend Activities Weekday Activities Sewer Work on Western Ave. Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston…Continue Reading Week of March 24, 2025
Week of March 17, 2025
175 North Harvard Street, 100 South Campus Drive The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART)….Continue Reading Week of March 17, 2025
Week of March 17, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Utility Investigation at HBS Enterprise Research Campus Residential/Hotel Weekend Activities Weekend Activities Weekday Activities Laboratory and Office Buildings. Weekend Activities Weekday Activities Greenway Weekend Activities Weekday Activities Treehouse Conference Center Weekend Activities Weekday Activities Building Mock-Ups Eversource Conduit Project General o Drones will be operated…Continue Reading Week of March 17, 2025