175 North Harvard Street, 100 South Campus Drive The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART)….Continue Reading Week of March 10, 2025
Week of March 10, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank HBS Utility Investigation Enterprise Research CampusResidential/HotelWeekend Activities Weekday Activities Laboratory and Office Buildings.Weekend Activities Weekday Activities Greenway Treehouse Conference CenterWeekend Activities Weekday Activities Building Mock-Ups Eversource Conduit Project General Signage Project at SEC and Stadium Way North Allston Storm Drain Extension Project (NASDEP)The NASDEP,…Continue Reading Week of March 10, 2025
Week of March 10, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of March 10. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 3/10/25-3/15/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of March 10, 2025