Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus Residential/HotelHoliday Weekend Activities Weekday Activities Laboratory and Office Buildings.No construction work will be taking place this holiday weekend.Weekday Activities Treehouse Conference CenterHoliday Weekend Activities Weekday Activities Greenway Streetscape Western Ave Utility and Roadway Work Building Mock-Ups Eversource Conduit Project General Signage…Continue Reading Week of April 21, 2025
Week of April 21, 2025
175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of April 21, 2025
Week of April 22, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of April 22. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 4/22/25-04/26/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of April 22, 2025