The following summarizes the work planned at 12 Palmer St for the week of May 5. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/05/25 – 5/10/25 Public Way Impacts: • Short-term scaffolding delivery will be on Monday, May 5. • No major road closures are anticipated. Exterior Site Activities:…Continue Reading Week of May 5, 2025
Week of May 5, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 5. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/05/25-05/10/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of May 5, 2025
Week of May 5, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday Activities Laboratory and Office Buildings. Weekday Activities Treehouse Conference CenterWeekend Activities Weekday Activities Greenway Streetscape Building Mock-Ups Nighttime Fiberoptic Manhole Work Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water…Continue Reading Week of May 5, 2025