175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of May 26, 2025
Week of May 26, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 26. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/26/25-6/1/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of May 26, 2025
Week of May 26, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday Activities Laboratory and Office Buildings. Weekday Activities Treehouse Conference CenterWeekend Activities Weekday Activities Greenway StreetscapeWeekend Activities Weekday Activities Evening Fiberoptic Manhole Work Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed…Continue Reading Week of May 26, 2025