Month: May 2025

Week of May 12, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise.  Week Of: 5/12/25 – 5/16/25Public Way Impacts:•    Scaffolding delivery will be scheduled this week, date TBD.•    No major road closures are anticipated. Exterior Site Activities: •    Masons will be…Continue Reading Week of May 12, 2025

Week of May 19, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 19. Please note that items in BOLD are expected to generate some noticeable noise.  Week Of: 5/19/25 – 5/23/25Public Way Impacts:• No Consigli road closures are anticipated.• We have been told that Bank of America is expecting to close Palmerstreet for a…Continue Reading Week of May 19, 2025

Week of May 19, 2025

The following summarizes the utility work planned in the Littauer Lot for the week of May 19. Please note that items in BOLD are expected to generate some noticeable noise Dates: 5/19/25-5/23/25 PUBLIC WAY IMPACTS: 1. Workzones will be coned off at several manhole locations in the Littauer lot so work can safely take plan inside the…Continue Reading Week of May 19, 2025

Week of May 19

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/19/25-5/24/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of May 19

Week of May 19, 2025

175 North Harvard Street Project Construction Impacts UpdateThe following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART): • Window installation using boom lifts continues. Exterior wall framing and sheathing continues up…Continue Reading Week of May 19, 2025

Week of May 12

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/12/25-05/17/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of May 12

Allston Development Monthly Update May 2025

Enterprise Research Campus Phase A Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update May 2025

Week of May 12, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday Activities  Laboratory and Office Buildings. Weekday Activities Treehouse Conference CenterWeekend Activities Weekday Activities Greenway Streetscape Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC)…Continue Reading Week of May 12, 2025

Week of May 12, 2025

175 North Harvard Street Project Construction Impacts UpdateThe following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART): • Window installation using boom lifts continues. Exterior wall sheathing continues. Exterior swing staging…Continue Reading Week of May 12, 2025