The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 30. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 6/30/25-7/6/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 30, 2025
Week of June 30, 2025
175 North Harvard Street Project Construction Impacts Update Week of June 30, 2025 The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of June 30, 2025
Week of June 30, 2025
The following summarizes the work planned at 12 Palmer St for the week of June 30. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 6/30/25 – 7/3/25 Public Way Impacts: • A vac truck will be used to excavate for the Eversource conduits on 7/1. The truck will be set…Continue Reading Week of June 30, 2025
Week of June 30, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities Weekday/Night Activities Evening Thermal Work GreenwayWeekend Activities Weekday Activities StreetscapeWeekend Activities Weekday/Night Activities Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP,…Continue Reading Week of June 30, 2025
Week of June 30, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, June 30: Dates: 06/30/25-07/06/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of June 30, 2025
Week of June 30, 2025
The following summarizes the work planned for the New FAS Building for the week of June 30. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 6/30/25-7/4/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of June 30, 2025
Week of June 23, 2025
The following summarizes the work planned for the New FAS Building for the week of June 23. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 6/23/25-6/27/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of June 23, 2025
Week of June 23, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, June 23: Dates: 06/23/25-06/29/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of June 23, 2025
Week of June 23, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 23. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 6/23/25-6/28/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 23, 2025
Week of June 23, 2025
The following summarizes the work planned at 12 Palmer St for the week of June 23. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 6/23/25 – 6/27/25 Public Way Impacts: • No major public way impacts. Exterior Site Activities: • The sitework contractor will be removing pavers within the fence…Continue Reading Week of June 23, 2025