GENERAL OCCUPANT INFORMATION PLAZA WORK: Week of 9/29/2025 IMPACTS– high noise levels from chipping, cutting and grinding will be most noticeable north of building footprint. A vacuum truck will produce elevated noise levels. INTERIOR WORK: Week of 9/29/2025 IMPACTS- medium noise levels from cutting, chipping and grinding…Continue Reading Week of September 29, 2025
Week of September 29, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus Residential/Hotel Weekend Activities Weekday/Night Activities Laboratory and Office Buildings Weekend Activities Weekday Activities Treehouse Conference Center Weekend Activities Weekday/Night Activities Greenway Weekend ActivitiesOn Saturday, September 27, masons will be working on the footing forms at the bio-swale area. Weekday Activities Streetscape…Continue Reading Week of September 29, 2025
Week of September 29, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, September 29, 2025: Dates: 09/29/25 – 10/05/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of September 29, 2025
Week of September 29, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 29. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/29/25 – 10/3/25 Temporary Public Way Impacts: Exterior Site Activities: Other Impacts: Work Hours:…Continue Reading Week of September 29, 2025
Week of September 29, 2025
The following summarizes the work planned for the new FAS building for the week of September 29, 2025: Dates: 9/29/25 – 10/3/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of September 29, 2025
Adams House Final Notice
Dear Neighbors: As part of Harvard House Renewal’s multi-phase renovation of Adams House, work on Russell Hall, Library Commons, and Westmorly Court at 26 Plympton/13-21 Bow Street is now substantially complete. As a reminder, the project’s scope was exterior restoration of the buildings, including new roofs, rebuilding chimneys, dormers, and repointing the brick facade, and…Continue Reading Adams House Final Notice
Week of September 22, 2025
GENERAL BUILDING OCCUPANT INFORMATION PLAZA WORK: Week of 9/22/2025 IMPACTS- high noise level from chipping, cutting, and grinding will be most noticeable north of building footprint. INTERIOR WORK: Week of 9/22/2025 IMPACTS- medium noise level from cutting, chipping, and grinding….Continue Reading Week of September 22, 2025
Week of September 22, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus Residential/Hotel Weekend Activities Weekday/Night Activities Laboratory and Office Buildings Weekend Activities Weekday Activities Treehouse Conference Center Weekend Activities Weekday/Night Activities Greenway Weekend Activities On Saturday, September 20, pavers will be installed on the shared-use path, and reclaimed boulders will be installed. Weekday…Continue Reading Week of September 22, 2025
Week of September 22, 2025
175 North Harvard Street Project The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of September 22, 2025
Week of September 22, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, September 15, 2025: Dates: 09/22/25 – 09/28/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of September 22, 2025