Enterprise Research CampusResidential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities in Coordination with Treehouse Operations Weekday Activities in Coordination with Treehouse Operations GreenwayWeekend Activities Weekday Activities Streetscape and Western AvenueWeekend Activities Weekday/night Activities Building Mock-Ups General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for…Continue Reading Week of November 17, 2025
Week of November 17, 2025
175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of November 17, 2025
Week of November 17, 2025
GENERAL OCCUPANT INFORMATION 1. Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM 2. The plaza renovation project is targeting an end of May 2026 completion…Continue Reading Week of November 17, 2025
Week of November 17, 2025
The following summarizes the work planned for the new FAS building for the week of November 17, 2025: Dates: 11/17/25 – 11/21/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of November 17, 2025