Enterprise Research Campus
Residential/Hotel
Weekend Activities
- On Saturday, November 15, fit out will take place in the hotel lobby and bars on floors 1 and 16. A crane in the lane way will finish raising material to the podium and leave the site.
- On Sunday, November 16, a crew of seven will be inside the hotel working on wall coverings.
Weekday/Night Activities
- Trotting Avenue is open to the public as the midrise and highrise residential buildings (Verra) continue to be occupied.
- Paver, planter and other installations will continue on the podium between the buildings.
- Punch list work is finishing in the midrise and continuing in the highrise and hotel.
- Fit out work continues in the highrise.
- Elevator work is underway.
- The hotel received its temporary certificate of occupancy.
- Fit out and finish work continue at the hotel.
- Planting deliveries and installation continues.
- Garage clean-up and finish work is underway.
- Furniture and other operator supplies are being delivered to the hotel.
Laboratory and Office Buildings
Weekend Activities
- On Saturday, November 15, terrace, exterior level 1 hardscape, penthouse mechanical, elevator, interior lobby and miscellaneous work will be underway.
- On Sunday, November 16, four electrician programmers and ten elevator installers will be working.
Weekday Activities
- Preparation and clean-up for testing and inspections will be ongoing. Boston Fire Department tests including fire-alarm testing are typically required to be scheduled off hours and may generate some noise.
- Terrace paver and finish work continues.
- Elevators are being adjusted and inspected.
- MEP detail and start up activities are ongoing.
- Mechanical penthouse detail and start up activities continue.
- Lobby and other fit out detail work continues.
- Garage finish work continues.
- Paver installation to finish on Trotting Avenue.
- Punch-list work is underway on the building’s interior and exterior as well as on the land/hardscaping areas.
Treehouse Conference Center
Weekend Activities in Coordination with Treehouse Operations
- On Saturday, November 15, boom lifts will be completing façade punch-list work, installing pavers/pedestals on the third-floor terrace and working on interior punch-list items
- On Sunday, November 16, no work will take place.
Weekday Activities in Coordination with Treehouse Operations
- Interior and operational punch list activity will continue.
- Roof detail and terrace paver installation continue.
- Façade punch list detail work will take place.
- Exterior landscaping/hardscaping detail will be underway.
- Loading dock activities will finish.
- Operational deliveries and work will take place.
Greenway
Weekend Activities
- On Saturday, November 15, pavers will be installed.
- On Sunday, November 16, no work will take place.
Weekday Activities
- Remaining shrubs will be planted.
- Pavers continue to be installed at the water features area.
- Decorative stonework will continue.
- Pavers will be placed
- Bioswale deck, concrete footings and plantings will be placed.
- Punchlist work has begun.
Streetscape and Western Avenue
Weekend Activities
- On Saturday, November 15, no work will take place.
- On Sunday, November 16, no work will take place.
Weekday/night Activities
- Prepping for mill and overlay paving including sidewalk ramps and conduit install on the Harvard Business School side of Western Avenue will continue.
- Barriers and fencing near the Treehouse will be removed after as landscaping finishes.
- Sidewalk crews will begin working between Milestone Street and the National Resilience entrance.
- Shrub, benches and amenity installation will be ongoing at Milestone and Trotting North.
Building Mock-Ups
- Preparations are underway to remove the building mockups on the corner of Hague and Rotterdam Streets. The demolition work will take place from inside the Hague Street lot.
General
- The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m. Crews will coordinate work in accordance with building operations for those buildings that have opened.
- Drones will be in use bi-weekly to monitor construction progress on site.
- Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
- Weekly flights are weather dependent and are scheduled one weekday morning.
- A drone is scheduled to fly on Thursday, November 20 at 3 p.m.
North Allston Storm Drain Extension Project (NASDEP)
The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
- South of Science work between Rena Path and Rotterdam Street is complete.
- Traffic markings will be completed.
92 Seattle Street
- The building is occupied.
- Flooring contractor will mobilize at an occupant agreed upon time.
- A crew addressed a leak in the wind driven rain, and the situation will continue to be monitored.
175 North Harvard Street Project Construction
The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
- Exterior swing staging and a scaffolding lift system are being removed where curtainwall installation and masonry are complete. Scaffolding is set up and curtainwall is underway on the north side of the site (the Harvard track side) inside the tarped working enclosure. Temporary heaters will be set up in this area. Brick is topped off on the low-rise and will be topped off on the mid-rise later this fall. The southside of the tower will be topped out by Thanksgiving. Three cranes are supporting the brick installation. A crane recently moved from the west side to the north side of the building to feed the tower. Brickwork is moving up the building. Mechanical, electrical, and plumbing trades continue working on multiple levels. Miscellaneous deliveries to the hoist will continue. The hoist will be taken down in the first week of January. Elevators are progressing for a November turnover. Finishing work on the lower floors is ongoing. Drywall work continues and dry wall deliveries take place on Wednesdays from 3 p.m. to 6 p.m. and on Saturdays. Drywall should be completed by the end of the year. Interior fit outs and framing beginning on lower floors continue throughout the building. Window installation is complete. Kitchen and bathroom work is underway. Utility drainage work continues. Work on the bike pavilion has started. Ramp work in the garage will start soon. Lighting has been adjusted to account for the shorter days. After Thanksgiving, crews will be mostly working in the interior of the building.
- PLEASE NOTE: South Campus Drive will be closed to vehicles during regular work hours through May 2026 from 7:00 a.m. to 4:00 p.m. to accommodate crane access and large delivery vehicles. The road will be open to traffic each day after 5:00 p.m. Adjustments have been made to roadway lighting to account for the shorter days.
- Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will remain a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
- When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
- A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
- Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
- On the new American Repertory Theater (ART) work site, mass timber structural installation is complete. Detailing work will continue through November. Masons are working on walls. A crane will be on site starting on Wednesday for a few weeks to assist with masonry. A second crane will come on site on Wednesday and Thursday for fly-tower staging. Acoustic metal decking continues on level one. Roofing is underway and roofing materials are delivered by crane once per week. All mechanical, electrical, and plumbing trades are mobilized. Drywall work is taking place. Exterior façade work is underway. Staging is up to support the brick façade work. Brick façade work will wrap mid-November on the west side or the back side of the building. Brick work will be complete on the Harvard track side of the building in December. Wood protection trades and mechanical systems installation continue. Concrete slab placement continues. Exterior steel for the east façade will take place. Exterior tarp protection at openings is being installed throughout the building. Curtain wall systems are ongoing around the east side (the North Harvard Street side) of the building. Miscellaneous steel is coming into the west stage setting up the overhead balconies and catwalk systems. This work will go into November/December. The building is scheduled to be weather-tight in December. A crane will be on site on Monday, November 10, to feed scaffolding up to the roof to work on the exterior fly tower. Daily steel, and block deliveries continue. Skylight and framing work continues. This work will be completed before the brick façade work begins on the chimneys. Concrete placements are ongoing.
- From Monday, November 10, and Wednesday, November 12 through Friday, November 14, workers will be removing a concrete wall on the Ivy Lane side of the job site using air compressing chipping guns. Some above normal noise can be expected during this work. The project team appreciates the community’s understanding during this necessary work.
- Drones are flying over the site on a bi-weekly basis to capture project progress.
- Work will be taking place at the affiliate housing building on Saturdays, November 8 and November 15, doing mechanical, electrical, and plumbing work, exterior masonry, some interior finish trades and general clean up. Some Saturday work can be expected each week going forward. Road closures are not anticipated on Saturdays.
- A crew at the ART project will be working on Saturday, November 8, continuing mass timber detailing, curtain wall, and general clean up. Saturday work can be expected through the winter.
- Both job sites will be closed on Tuesday, November 11, in observance of the Veterans Day holiday.
- There are no plans to work at the affiliate housing building on Sunday, November 9 or November 16. There is no work taking place at the building mock-up across North Harvard Street.
- The projects are under camera surveillance, with live monitoring and audible messaging.
- The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
- Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
210 North Harvard Street
- Eversource or Verizon will remove an old pole and power line.
- The bakery Sofra is open.
168 Western Ave
- Minor punch list is ongoing.
100 Holton Street
- A roofing project on two back older sections of the roof of 100 Holton St started on September 2.
- Crews will be working the next three Saturdays, November 15, 22, and 29.
- Crews are more than 60 percent through making repairs and applying a liquid applied roofing membrane on the roof above Red Sky Studios and other businesses at the back of the building closer to Everett Street.
- Targeting project completion in December.
- Storm project will take place next spring.