175 North Harvard Street Project ConstructionThe following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Weeks of December 22, 29, 2025 and January 9, 2026
Weeks of December 22, 29 2025, and January 9, 2026
Construction Impacts Update Weeks of December 22 and 29, 2025 and January 5, 2026 DEF Extension into Harvard Business School Enterprise Research Campus Residential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities in Coordination with Treehouse Operation Weekday Activities in Coordination with Treehouse Operation GreenwayWeekend Activities Weekday Activities Streetscape…Continue Reading Weeks of December 22, 29 2025, and January 9, 2026
Week of December 22, 2025
Dates: 12/22/25-12/26/25 KIRKLAND HOUSE IMPACTS: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of December 22, 2025
Week of December 22, 2025
The following summarizes the work planned at 12 Palmer St for the week of December 22. Please note that items in BOLD are expected to generate some noticeable impacts. Week Of: 12/22/25 – 12/26/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of December 22, 2025