The following summarizes the work planned at Eliot House during the week beginning Monday, July 21: Dates: 07/21/25-07/27/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of July 21, 2025
Week of July 21, 2025
Dates: 7/21/25-7/27/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of July 21, 2025
Week of July 21, 2025
The following summarizes the work planned for the New FAS Building for the week of July 21. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 7/21/25-7/25/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of July 21, 2025
Week of July 21, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities Weekday/Night Activities GreenwayWeekend Activities Weekday Activities StreetscapeWeekday Activities Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston…Continue Reading Week of July 21, 2025
Week of July 14, 2025
The following summarizes the work planned at 12 Palmer St for the week of July 14. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 7/14/25 – 7/18/25 Public Way Impacts: • No major public way impacts are expected Exterior Site Activities: • A compressor will be running during work hours…Continue Reading Week of July 14, 2025
Week of July 14, 2025
The following summarizes the work planned for the New FAS Building for the week of July 14. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 7/14/25-7/18/25PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of July 14, 2025
Week of July 14, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday/Night Activities Laboratory and Office BuildingsWeekend Activities Weekday Activities Treehouse Conference CenterWeekend Activities Weekday/Night Activities GreenwayWeekend Activities Weekday Activities StreetscapeWeekend Activities Weekday Activities Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed…Continue Reading Week of July 14, 2025
Week of July 14, 2025
175 North Harvard Street Project Construction Impacts UpdateThe following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of July 14, 2025
Allston Development Monthly Update May 2025
Enterprise Research Campus Phase A Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update May 2025
Allston Development Monthly Update July 2025
Enterprise Research Campus Phase A Development work is underway of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research and…Continue Reading Allston Development Monthly Update July 2025