175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of November 17, 2025
Week of November 17, 2025
GENERAL OCCUPANT INFORMATION 1. Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM 2. The plaza renovation project is targeting an end of May 2026 completion…Continue Reading Week of November 17, 2025
Week of November 17, 2025
The following summarizes the work planned for the new FAS building for the week of November 17, 2025: Dates: 11/17/25 – 11/21/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of November 17, 2025
Week of November 10, 2025
175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of November 10, 2025
Week of November 10, 2025
GENERAL OCCUPANT INFORMATION PLAZA WORK: Week of 11/10/25 IMPACTS– high noise level from chipping, cutting and grinding will be most noticeable in the north of building footprint. INTERIOR WORK: Week of 11/10/25 IMPACTS- medium noise level from cutting, chipping and grinding…Continue Reading Week of November 10, 2025
Allston Development Monthly Update November 2025
Enterprise Research Campus Phase A Development work continues at the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A consists of two lab buildings designed for research and development; two…Continue Reading Allston Development Monthly Update November 2025
Allston Development Update October 2025
Enterprise Research Campus Phase A Development work continues at the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A consists of two lab buildings designed for research and development; two…Continue Reading Allston Development Update October 2025
Week of November 3, 2025
175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of November 3, 2025
Week of November 3, 2025
The following summarizes the work planned at 12 Palmer St for the week of November 3. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/3/25 – 11/7/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Work Hours:…Continue Reading Week of November 3, 2025
Week of November 3, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, November 3, 2025: Dates: 11/03/25 – 11/07/2025 KIRKLAND HOUSE IMPACTS: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: 11/01/25 WORK HOURS:…Continue Reading Week of November 3, 2025