175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Weeks of October 6 and 13, 2025
Week of September 29, 2025
175 North Harvard Street Project Construction Impacts The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of September 29, 2025
Week of October 20, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, October 20, 2025: Dates: 10/20/25 – 10/26/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of October 20, 2025
Week of October 20, 2025
The following summarizes the work planned for the new FAS building for the week of October 20, 2025: Dates: 10/20/25 – 10/24/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of October 20, 2025
Week of October 13
GENERAL OCCUPANT INFORMATION PLAZA WORK: Week of 10/13/25 IMPACTS– high noise level from chipping, cutting and grinding will be most noticeable in N of building footprint. Vacuum truck will produce elevated noise levels. INTERIOR WORK: Week of 10/13/25 IMPACTS- medium noise level from cutting, chipping and grinding CONTACTS:…Continue Reading Week of October 13
Week of October 13, 2025
The following summarizes the work planned at 12 Palmer St for the week of October 13. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/13/25 – 10/17/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.• Eversource will have a crew excavating for underground conduits onPalmer Street…Continue Reading Week of October 13, 2025
Week of October 13, 2025
Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/Hotel Weekend Activities Weekday/Night Activities Laboratory and Office Buildings Weekend Activities Weekday Activities Treehouse Conference Center Weekend Activities Weekday/Night Activities Greenway Weekend Activities Weekday Activities Streetscape and Western Avenue Weekend Activities Weekday/night Activities Building Mock-Ups General North Allston Storm Drain Extension Project…Continue Reading Week of October 13, 2025
Week of October 13, 2025
The following summarizes the work planned at Eliot House during the week beginning Monday, October 13, 2025: Dates: 10/13/25 – 10/19/25 PUBLIC WAY IMPACTS: *MONDAY OCTOBER 13th IS A HOLIDAY AND THE JOBSITE WILL BE CLOSED FOR BOTH SHIFTS* EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: Weekend Activities: WORK HOURS:…Continue Reading Week of October 13, 2025
Week of October 13, 2025
The following summarizes the work planned for the new FAS building for the week of October 13, 2025: Dates: 10/13/25 – 10/17/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of October 13, 2025
Week of October 6, 2025
GENERAL OCCUPANT INFORMATION PLAZA WORK: Week of 10/6/25 IMPACTS- high noise level from chipping, cutting and grinding will be most noticeable in the north of building footprint. A vacuum truck will produce elevated noise levels. INTERIOR WORK: Week of 10/6/25 IMPACTS- medium noise level from cutting, chipping and grinding…Continue Reading Week of October 6, 2025