Week of May 26, 2025

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 26. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/26/25-6/1/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of May 26, 2025

Week of May 26, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research CampusResidential/HotelWeekend Activities Weekday Activities Laboratory and Office Buildings. Weekday Activities Treehouse Conference CenterWeekend Activities Weekday Activities Greenway StreetscapeWeekend Activities Weekday Activities Evening Fiberoptic Manhole Work Building Mock-Ups Eversource Conduit Project General North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed…Continue Reading Week of May 26, 2025

Week of May 12, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise.  Week Of: 5/12/25 – 5/16/25Public Way Impacts:•    Scaffolding delivery will be scheduled this week, date TBD.•    No major road closures are anticipated. Exterior Site Activities: •    Masons will be…Continue Reading Week of May 12, 2025

Week of May 19, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 19. Please note that items in BOLD are expected to generate some noticeable noise.  Week Of: 5/19/25 – 5/23/25Public Way Impacts:• No Consigli road closures are anticipated.• We have been told that Bank of America is expecting to close Palmerstreet for a…Continue Reading Week of May 19, 2025

Week of May 19, 2025

The following summarizes the utility work planned in the Littauer Lot for the week of May 19. Please note that items in BOLD are expected to generate some noticeable noise Dates: 5/19/25-5/23/25 PUBLIC WAY IMPACTS: 1. Workzones will be coned off at several manhole locations in the Littauer lot so work can safely take plan inside the…Continue Reading Week of May 19, 2025

Week of May 19

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/19/25-5/24/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of May 19