Day: January 9, 2026

Week of January 12, 2026

DEF Extension into Harvard Business School Enterprise Research Campus ERC Balance 1.4 Streetscape North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, completed the enabling phase of the project from Rena Path and to the…Continue Reading Week of January 12, 2026

Week of January 12, 2026

GENERAL OCCUPANT INFORMATION 1.    Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM 2.    The plaza renovation project is targeting an end of May 2026 completion date. 3.    The…Continue Reading Week of January 12, 2026