175 North Harvard Street Project ConstructionThe following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of January 12, 2026
Week of January 12, 2026
DEF Extension into Harvard Business School Enterprise Research Campus ERC Balance 1.4 Streetscape North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, completed the enabling phase of the project from Rena Path and to the…Continue Reading Week of January 12, 2026
Week of January 12, 2026
GENERAL OCCUPANT INFORMATION 1. Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM 2. The plaza renovation project is targeting an end of May 2026 completion date. 3. The…Continue Reading Week of January 12, 2026