GENERAL OCCUPANT INFORMATION 1. Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m. Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM 2. The plaza renovation project is targeting an end of May 2026 completion date. 3. The…Continue Reading Week of January 19, 2026
Week of January 20, 2026
The following summarizes the work planned at Eliot House during the week beginning Tuesday, January 20, 2026: KIRKLAND HOUSE IMPACTS: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 20, 2026
Week of January 20, 2026
The following summarizes the work planned for the new FAS building for the week of January 20, 2026: Dates: 1/20/26 – 1/23/26 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of January 20, 2026
Greenleaf House January 2026 Update
This is an update regarding the renovation project at Greenleaf House; Radcliffe Institute’s dean’s residence located at 76 Brattle Street. Work is progressing as planned and is on track for completion in July 2026. As a reminder, the scope of the project consists of full exterior and interior renovations, as well as site and landscaping…Continue Reading Greenleaf House January 2026 Update
Week of January 12, 2026
The following summarizes the work planned at 12 Palmer St for the week of January 12. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 1/12/26 – 1/16/26 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of January 12, 2026
Week of January 12, 2026
The following summarizes the work planned at Eliot House during the week beginning Monday, January 12, 2026: KIRKLAND HOUSE IMPACTS: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 12, 2026
Week of January 12, 2026
175 North Harvard Street Project ConstructionThe following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of January 12, 2026
Week of January 12, 2026
DEF Extension into Harvard Business School Enterprise Research Campus ERC Balance 1.4 Streetscape North Allston Storm Drain Extension Project (NASDEP)The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, completed the enabling phase of the project from Rena Path and to the…Continue Reading Week of January 12, 2026
Week of January 12, 2026
GENERAL OCCUPANT INFORMATION 1. Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM 2. The plaza renovation project is targeting an end of May 2026 completion date. 3. The…Continue Reading Week of January 12, 2026
Week of January 12, 2026
The following summarizes the work planned for the new FAS building for the week of January 12, 2026: Dates: 1/12/26 – 1/17/26 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of January 12, 2026