Dear Neighbors: As part of Harvard House Renewal’s multi-phase renovation of Adams House, work on Russell Hall, Library Commons, and Westmorly Court at 26 Plympton/13-21 Bow Street is now substantially complete. As a reminder, the project’s scope was exterior restoration of the buildings, including new roofs, rebuilding chimneys, dormers, and repointing the brick facade, and…Continue Reading Adams House Final Notice
Week of July 28, 2025
Dates: 7/28/25-8/2/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of July 28, 2025
Week of July 21, 2025
Dates: 7/21/25-7/27/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of July 21, 2025
Week of July 7, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of July 7. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 7/07/25-7/12/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of July 7, 2025
Week of June 30, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 30. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 6/30/25-7/6/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 30, 2025
Week of June 23, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 23. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 6/23/25-6/28/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 23, 2025
Week of June 16, 2025
Dates: 6/16/25-6/21/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 16, 2025
Week of June 9, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 9. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 6/9/25-6/14/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 9, 2025
Week of June 2, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 2. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 06/02/25-06/07/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 2, 2025
Week of May 26, 2025
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of May 26. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 5/26/25-6/1/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS:…Continue Reading Week of May 26, 2025