The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 26th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 26, 2024
Week of February 19, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 19th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 19, 2024
Week of February 12, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 12th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 12, 2024
Week of February 5, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 5th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of February 5, 2024
Week of January 29, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 29th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 29, 2024
Week of January 22, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 22nd. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 22, 2024
Week of January 15, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 15th . Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 15, 2024
Week of January 8, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 8th . Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 8, 2024
Week of January 1, 2024
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 1st. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of January 1, 2024
Week of December 25, 2023
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 25th. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of December 25, 2023