Week of February 26, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 26th. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Trucking of soils and concrete will continue next week from Bow Street-Gate 2.
  • Crane for roofer scheduled for next Monday and Thursday at Gate 2.
  • Concrete pump truck scheduled for next Tuesday at Gate 2.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Cutting along the East and South of Westmorly Hall.
  • Roofing contractor will continue abatement and demolition of the slate roof on Russell Hall.
  • Scaffolding for Russell Hall Chimney Re-Builds will continue.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm and Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  1. Interior wood framing will continue in Westmorly Hall.
  2. Drywall and framing will continue within Westmorly Hall.
  3. Excavations within Russell Hall basement will continue.
  4. Excavations for under slab utilities within Westmorly Hall will continue.
  5. Excavations for new footings will begin at North Westmorly Hall.
  6. Excavations for new elevator #1 in Westmorly Hall will begin.
  7. Rebar & concrete work is ongoing.
  8. Mechanical contractors will continue with installation of new systems within Westmorly Hall.

WORK HOURS:

  1. Monday to Friday: 7:00am to 3:30pm
  2. Saturday 3/2 – 9:00am to 4:30pm