Week of January 8, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 8th . Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Trucking of soils and concrete will continue from Bow Street Gate 2.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Cutting along the north, west and south elevations of the Library Commons and washing on east elevation of Westmorly Hall.
  • Scaffolding installation will continue on the east elevation of Westmorly Hall and south elevation of Russell Hall.
  • Crane for temporary steel at back parking lot is scheduled for the middle of the week.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm and Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly Hall.
  • Interior demolition of concrete in Russell Hall.
  • Demolition of Westmorly North Levels 2 & 3.
  • Abatement will continue within the project at Russell Hall, Library, Dining Hall and Westmorly Hall.
  • Drywall ignition barrier will continue on the 3rd & 4th floor of Westmorly Hall.
  • Excavations within Russell Hall basement will continue.
  • Excavations for under slab utilities within Westmorly Hall will continue.

WORK HOURS:

  • Tuesday to Friday: 7:00am to 3:30pm
  • Saturday 1/13 – 9:00am to 4:30pm