Week of December 25, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 25th. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  1. Continuous deliveries and dumpster swaps will take place throughout the week.
  2. Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  3. Trucking of soils and concrete will continue to occur from Bow Street Gate 2.

EXTERIOR SITE ACTIVITIES:

  1. Masonry work on the exterior façade will continue, which includes cutting along the North, West and South Elevations.
  2. The installation of scaffolding is ongoing on the East Elevation.
  3. A crane is tentatively scheduled to be onsite Wednesday – Friday for temporary steel at back parking lot.
  4. Man/material hoist will be operating while the site is open.
    1. On weekdays the lift will operate between the hours of 7:00am-3:30pm and on Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  1. Interior rough carpentry will continue.
  2. Interior demolition of Westmorly and Russell Halls continues.
  3. Abatement is ongoing within the project (Russell Hall, Library, Dining Hall and Westmorly).
  4. Drywall activities in Westmorly Hall will take place early in the week.
  5. Excavations within Russell Hall’s basement remain ongoing.
  6. Excavations for under slab utilities within Westmorly Hall will take place.

WORK HOURS:

  1. Jobsite will be closed Monday 12/25 for Christmas Holiday
  2. Tuesday to Friday: 7:00am to 3:30pm
  3. Saturday 12/30 – 9am to 4:30pm