Week of January 1, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 1st. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Trucking of soils and concrete will continue at Gate 2 on Bow Street.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue, which includes cutting along the north, west and south elevations of the Library Commons.
  • Scaffolding installation will continue on the east elevation of Westmorly.
  • A crane is tentatively scheduled to be onsite in the middle of the week for temporary steel at back parking lot.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm and Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly.
  • Interior demolition of Library and Dining Hall areas. 
  • Demolition of Westmorly North levels 2 and 3 is scheduled to start the end of the week into Saturday.
    • A lull will be operating in the back parking lot for this operation.
  • Abatement is ongoing within the project (Russell Hall, Library, Dining Hall and Westmorly).
  • Drywall ignition barriers installation in Westmorly Hall will continue on the 4th floor.
  • Excavations within Russell Hall’s basement remain ongoing.
  • Excavations for under slab utilities within Westmorly Hall will take place.

WORK HOURS:

  • Jobsite Closed Monday 1/1 for New Years Day
  • Tuesday to Friday: 7:00am to 3:30pm
  • Saturday 1/6 – 9am to 4:30pm