Category: Enterprise Research Campus (ERC) Utility Enabling Work

Week of June 24, 2024

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank  Enterprise Research Campus (ERC)   92 Seattle Street   175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot Expansion  Construction has begun on the new American Repertory Theater (ART), which will be located at the front of the 175 North Harvard parcel with the new Harvard…Continue Reading Week of June 24, 2024

Week of June 17, 2024

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot Expansion Construction has begun on the new American Repertory Theater (ART), which will be located at the front of the 175 North Harvard parcel with the new Harvard…Continue Reading Week of June 17, 2024

Week of June 10, 2024

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot ExpansionConstruction has begun on the new American Repertory Theater (ART), which will be located at the front of the 175 North Harvard parcel with the new Harvard University…Continue Reading Week of June 10, 2024

Week of June 3, 2024

The Western Avenue utility crossing roadway and Kresge Way phase of infrastructure work is finishing up with inspections and punch list work in coordination with University operations.   Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot…Continue Reading Week of June 3, 2024

Week of May 27, 2024

All sites will not be working on Memorial Day, Monday, May 27, 2024.   The Western Avenue utility crossing roadway and Kresge Way phase of infrastructure work is finishing up with inspections and punch list work in coordination with University operations.    Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank  Enterprise Research Campus (ERC)  92 Seattle…Continue Reading Week of May 27, 2024

Week of May 20, 2024

The Western Avenue utility crossing roadway and Kresge Way phase of infrastructure work is finishing up with inspections and punch list work in coordination with University operations.   Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot…Continue Reading Week of May 20, 2024

Week of May 13, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of May 13, 2024

Week of May 6, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of May 6, 2024

Week of April 29, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.   As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the…Continue Reading Week of April 29, 2024

Week of April 22, 2024

The Western Avenue utility crossing roadway work is finalized and is finishing up on Kresge Way and is being coordinated with University operations.    As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the main driveway into the HBS…Continue Reading Week of April 22, 2024