Public Way Impacts
- Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
- Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
- Linden Street and Plympton Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
- A site fence has been installed, including lighting and signage.
- Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
- Continuous deliveries will happen at Linden, Plympton, and Bow Streets.
Exterior Site Activities
- Work on the courtyard landscape and hardscape will continue.
- Sidewalk pavers will be set on Plympton Street and sidewalk curbing will be set on Linden Street, both with no impacts.
- Exterior light fixtures will be mounted.
- Exterior doors will be set.
Interior Site Activities
- Spray insulation on the ground floor remains ongoing.
- Punch list items will occur on the 1st, 2nd, and 3rd floors.
- Taping, plastering, and finishing is progressing on the 1st and 4th floor.
- Tile installation is continuing on the 1st and 2nd floor.
- Wood flooring continues to be installed on the 2nd and 1st floor.
- Installation of trim on the 1st and 2nd floor will continue to take place.
- Priming and applying the first coat of paint will occur.
- Restoration of the stairs is progressing.
- Window shades will be installed.
- Appliances, toilet accessories, bathroom mirrors, door handles, and additional hardware will be installed.
- Installation of elevator finishes continues.
- Installation of overhead rough-ins for electrical, plumbing, mechanical, Tel data, and fire protection will continue.