Public Way Impacts

  • Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
  • Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
  • Linden Street and Plympton Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
  • A site fence has been installed, including lighting and signage.
  • Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
  • Continuous deliveries will happen at Linden, Plympton, and Bow Streets.

 Exterior Site Activities

  • Work on the courtyard landscape and hardscape will continue.
  • Sidewalk pavers will be set on Plympton Street and sidewalk curbing will be set on Linden Street, both with no impacts.
  • Exterior light fixtures will be mounted.
  • Exterior doors will be set.

 Interior Site Activities

  • Spray insulation on the ground floor remains ongoing.
  • Punch list items will occur on the 1st, 2nd, and 3rd floors.
  • Taping, plastering, and finishing is progressing on the 1st and 4th floor.
  • Tile installation is continuing on the 1st and 2nd floor.
  • Wood flooring continues to be installed on the 2nd and 1st floor.
  • Installation of trim on the 1st and 2nd floor will continue to take place.
  • Priming and applying the first coat of paint will occur.
  • Restoration of the stairs is progressing.
  • Window shades will be installed.
  • Appliances, toilet accessories, bathroom mirrors, door handles, and additional hardware will be installed.
  • Installation of elevator finishes continues.
  • Installation of overhead rough-ins for electrical, plumbing, mechanical, Tel data, and fire protection will continue.