Week of March 6, 2023

Public Way Impacts

  • Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
  • Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
  • Linden Street and Plympton Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
  • A site fence has been installed, including lighting and signage.
  • Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
  • Continuous deliveries will happen at Linden, Plympton, and Bow Streets.

 Exterior Site Activities

  • Work on the courtyard landscape and hardscape remains ongoing.
  • Sidewalk curbing on Linden Street will continue to be set with no impact to the public.  

Interior Site Activities

  • Punch list items will continue to occur on the 1st, 2nd, and 3rd floors.
  • Spray insulation on the ground floor is ongoing.
  • Taping, plastering, and finishing will continue to take place on the ground floor.
  • Tile installation is continuing on the 1st and ground floor.
  • Wood flooring continues to be installed on the 1st floor.
  • Installation of trim will continue to take place on the 1st floor.
  • Priming and applying the first coat of paint is ongoing.
  • Application of finish paint will occur where applicable.
  • Restoration of the stairs is progressing.
  • Window shades will continue to be installed.
  • Appliances, toilet accessories, bathroom mirrors, door handles, and additional hardware will continue to be installed.
  • Overhead rough-ins for electrical, plumbing, mechanical, Tel data, and fire protection continues.