Week of March 20, 2023

Public Way Impacts

  • Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
  • Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
  • Linden Street and Plympton Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
  • A site fence has been installed, including lighting and signage.
  • Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
  • Continuous deliveries will happen at Linden, Plympton, and Bow Streets.
  • Linden Street will be closed to vehicular traffic on Monday, March 20, and Tuesday, March 21, between the hours of 7:00 a.m. and 4:00 p.m. for the installation of the sidewalk curb on Linden Street. An excavator will be positioned in the street to support this activity. The road will re-open to vehicles after 4:00 p.m. Vehicles trying to access Mt. Auburn St. from Mass. Ave will be detoured down Dunster Street. Pedestrians will have full access to Linden Street during this work.

 Exterior Site Activities

  • Work on the courtyard landscape and hardscape is progressing.
  • Sidewalk curbing on Linden Street continues to be set.

Interior Site Activities

  • Punch list items will continue to occur on the 1st, 2nd, and 3rd floors.
  • Taping, plastering, and finishing continues on the ground floor.
  • Tile installation on the 1st and ground floor is ongoing.
  • Wood flooring continues to be installed on the 1st floor.
  • Installation of trim will continue to take place on the 1st floor.
  • Priming and applying the first coat of paint is ongoing.
  • Application of finish paint will continue to occur where applicable.
  • Restoration of the stairs is progressing.
  • Window shades continue to be installed.
  • Appliances, toilet accessories, bathroom mirrors, door handles, and additional hardware will continue to be installed.
  • Overhead rough-ins for electrical, plumbing, mechanical, Tel data, and fire protection continues.