Week of April 24, 2023

Public Way Impacts

  • Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
  • Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
  • Linden Street and Plympton Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
  • A site fence has been installed, including lighting and signage.
  • Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
  • Continuous deliveries will happen at Linden, Plympton, and Bow Streets.
  • Linden Street will be closed on Wednesday, April 26, from 9pm to 5am so the contractor can cut and cap the old water main on Linden Street leading into Randolph Hall. Cambridge Water and Sewer needs to turn off a water valve that services some neighboring buildings. These abutters have been notified.
  • Linden Street between Mass Ave and Bow Street will be closed on Thursday, April 27, during standard work hours for re-paving.

 Exterior Site Activities

  • Work on the courtyard landscape and hardscape continues to progress.

Interior Site Activities

  • Punch list items continue on the 1st, 2nd, and 3rd floors.