The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 28. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of August 28, 2023
Week of August 28, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way,…Continue Reading Week of August 28, 2023
Week of August 21, 2023
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 21. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of August 21, 2023
Week of August 21, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way,…Continue Reading Week of August 21, 2023
Allston Development Monthly Update- August 2023
Enterprise Research Campus Phase ADevelopment work has begun at the parcel of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed for research…Continue Reading Allston Development Monthly Update- August 2023
Week of August 14, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility…Continue Reading Week of August 14, 2023
Week of August 14, 2023
The following summarizes the work planned on the Adams House Phase 3 renovation for the week of August 14. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of August 14, 2023
Week of August 7, 2023
The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility…Continue Reading Week of August 7, 2023
Week of August 7, 2023
The following update is a summary of the renovation work taking place at Russell Hall, Library Commons, and Westmorly Court (Adams House/Phase 3) next week: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: (Items in Bold are expected to generate some noticeable noise) INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of August 7, 2023