Week of August 7, 2023

The following update is a summary of the renovation work taking place at Russell Hall, Library Commons, and Westmorly Court (Adams House/Phase 3) next week:

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Eversource is scheduled to remove the gas meters from the building behind 22 Plympton Street.

EXTERIOR SITE ACTIVITIES: (Items in Bold are expected to generate some noticeable noise)

  • Civil contractor will be working on demo in the light court area.
  • Masonry work on the exterior façade will continue.
  • Abatement of windows and doors will continue.
  • Abatement of East Terrace walk-out bay roofs will start.
  • Water main work will start towards the end of the week at lower Bow Street.

INTERIOR ACTIVITIES:

  • Mechanical, electrical, and plumbing make safe and temp fire alarm / temp power will continue.
  • Temporary protection will continue.
  • Demo of interior wood trim, kitchen equipment and ancillaries will continue.

WORK HOURS:

  • Monday to Friday 7am to 3:30pm
  • Saturday 8/12 9am to 4:30pm