Week of July 31, 2023

The following update is a summary of the renovation work taking place at Russell Hall, Library Commons, and Westmorly Court (Adams House/Phase 3) next week:

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Eversource is scheduled to remove the gas meters from the building behind 22 Plympton Street.

EXTERIOR SITE ACTIVITIES:   (Items in Bold are expected to generate some noticeable noise)

  • The contractor will be working on excavating for new domestic & fire services this week using a vacuum truck from Monday through Wednesday.
  • Masonry work on the exterior Façade will continue.
  • Scaffolding erection will continue at the East Terrace and then the Southwest corner of Russell Hall.
  • Abatement of windows and doors will continue.
  • Removal of refrigerant from the servery cooling units.

INTERIOR ACTIVITIES:

  • Mechanical, electrical and plumbing make safe and temp fire alarm / Temp power will continue.
  • Temporary protection will continue.
  • Demo of interior wood trim, kitchen equipment and ancillaries will continue.

WORK HOURS:

  • Monday to Friday 7am to 3:30pm
  • Saturday 7/22 9am to 4:30pm