Month: July 2023

Week of July 31, 2023

The following update is a summary of the renovation work taking place at Russell Hall, Library Commons, and Westmorly Court (Adams House/Phase 3) next week: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES:   (Items in Bold are expected to generate some noticeable noise) INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of July 31, 2023

Week of July 31, 2023

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across…Continue Reading Week of July 31, 2023

Week of July 24, 2023

The following update is a summary of the renovation work taking place at Russell Hall, Library Commons, and Westmorly Court (Adams House/Phase 3) next week: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: (Items in Bold are expected to generate some noticeable noise) INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of July 24, 2023

Week of July 17, 2023

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western…Continue Reading Week of July 17, 2023

Week of July 17, 2023

The following update is a summary of the renovation work taking place at Russell Hall, Library Commons, and Westmorly Court (Adams House/Phase 3) next week: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: (Items in Bold are expected to generate some noticeable noise) INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of July 17, 2023

Week of July 10, 2023

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations. Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western…Continue Reading Week of July 10, 2023

Allston Development Monthly Update- July 2023

Enterprise Research Campus Phase ADevelopment work has begun at the parcel of the future Enterprise Research Campus (ERC) in Allston across from Harvard Business School (HBS) bordered by the Mass Pike, Western Avenue, Hague Street, and the National Resilience Inc. facility at 500 Soldiers Field Road. Phase A will consist of two lab buildings designed…Continue Reading Allston Development Monthly Update- July 2023