The following update is a summary of the renovation work taking place at Russell Hall, Library Commons, and Westmorly Court (Adams House/Phase 3) next week:
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Eversource is scheduled to remove the gas meters from behind the building.
- Install of crosswalk at the corner of Bow and DeWolfe and line striper for Plympton Street (Police Details will be scheduled)
- Removal of demo materials and live loading into dumpsters from back parking to Bow Street. (Police Details will be scheduled.)
- Note that the set-up during the trash-out will last 1 hour for 3 times a day approx. Sidewalk will be fully opened when plan is not in use.
EXTERIOR SITE ACTIVITIES: (Items in Bold are expected to generate some noticeable noise)
- Contractor will be working on test pits to identify underground utilities at Lower Bow Street using a vacuum truck.
- Masonry work on the exterior façade will continue.
- Scaffolding erection will continue at the East Terrace and then the Southwest corner of Russell Hall.
- Abatement of windows and doors will continue.
- Install of the temporary standpipes on the exterior of Russell and Westmorly will continue.
- Removal of refrigerant from kitchen and servery cooling units.
INTERIOR ACTIVITIES:
- Mechanical, electrical, and plumbing make safe and temp fire alarm / temp power will continue.
- Temporary protection will continue.
- Demo of interior wood trim, kitchen equipment and ancillaries will continue.
WORK HOURS:
- Monday to Friday 7am to 3:30pm
- Saturday 7/22 9am to 4:30pm