Monday 7/10:
- Continuing with the temp crosswalks and Jersey Barrier Placements
- Harvard has moving trucks scheduled to move tutors to Phase 2. Spots along Upper and Lower Bow will be secured for them
- Window Abatement from the Exterior will begin. Set-up only for Monday
Tuesday 7/11:
- Lower Bow will be officially closed off starting today along with the sidewalks. Signage will be installed.
- Continuing with the Temp Crosswalk Install and Jersey Barrier install
- Site Fence will be starting along Bow Street and Plympton Street
- Dumpster and Lull being Delivered for Demo Operations
- DeAngelis will be here to remove Plympton Street Gate – Possible lane closure at Plympton Street temporarily.
- Window Abatement will continue using Boom Lift
- Masonry Salvage work will begin at East Terrace
Wednesday 7/12:
- Continue with Site Fence Install
- Continue with Exterior Site Set-up
- Continue with Dumpster Swaps and Demo Operations
- Window Abatement will continue using Boom Lift
- Masonry Salvage work will continue at East Terrace
Thursday 7/13:
- Tentatively Scheduled to perform Test Pits for Man Material Lift at Lower Bow
- Window Abatement will continue using Boom Lift
- Continue with dumpster swaps for demo
- Masonry Salvage work will continue at East Terrace
- Removal of Sidewalks and site prep will continue
- Continue with Site Fence Install
Friday 7/14:
- Temp Standpipe Install will begin – will need access to back parking lot
- Window Abatement will continue using Boom Lift
- Continue with dumpster swaps for demo
- Masonry Salvage work will continue at East Terrace
- Removal of sidewalks and site prep will continue
- Continue with Site Fence Install
Saturday 7/15:
- All exterior and noisy work will start at 9am
- Continue with Masonry Salvage
- Continue with Site Prep and sidewalk removal
- Continue with Abatement if needed
- Continue with site fencing if needed.