Week of October 30, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of October 30. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Steel deliveries to the back parking lot will continue.
  • Eversource is scheduled to remove the existing gas main at the intersection of Bow Street and Arrow Street. 
    • This is an Eversource project and is permitted separately from the Adams Phase 3 Project. 
    • Jersey barriers along upper Bow Street will be reinstalled following this work.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
  • Scaffolding installation will continue along the west, south, and east elevations of Westmorly.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate until 6:00pm.
  • Steel erection at the roof Westmorly will continue. 
  • Dewatering equipment will be delivered to the site to begin the dewatering process.

INTERIOR ACTIVITIES:

  • Interior rough carpentry will continue.
  • Abatement will continue inside Russell Hall.
  • Interior demolition of Westmorly and Russell Hall.
  • Saw cutting and removal of Russell Hall Slab will continue.
  • Temporary heating equipment installed.

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 11/4 – 9:00am to 4:30pm