The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 13. Please note that items in BOLD are expected to generate some noticeable noise. PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of November 13, 2023
Week of November 13, 2023
175 North Harvard Street Project Construction Impacts Update The contractor started dismantling the building on Thursday, November 2, and this work is expected to take approximately four weeks. Materials are being sorted and trucked away from the job site. Due to the nature of the work and the equipment needed, noise can be expected during…Continue Reading Week of November 13, 2023