Week of November 13, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 13. Please note that items in BOLD are expected to generate some noticeable noise. 

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crew will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Eversource will continue the removal of the existing gas main at the intersection of Bow Street and Arrow Street.
    • This work is scheduled to take place Monday, November 13th.
    • This is an Eversource project and is permitted separately from the Adams Phase 3 Project. 
    • Following this work crews will complete a storm drain tie-in in this area.
    • Jersey barriers along upper Bow Street will be reinstalled following this work.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Washing activities will take place on the south elevation of Westmorly Hall.
  • Scaffolding installation will continue along North & West elevations of the Library.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7am-5pm and Saturday it will operate from 9am-4:30pm.
  • Steel erection at the fourth floor of Westmorly Hall will continue.
  • Dewatering equipment set up will continue at Russell Hall.
  • Crews will be onsite Tuesday, November 14, to set up temporary heating equipment in the alleyway adjacent to 22 Plympton Street.

INTERIOR ACTIVITIES:

  • Interior rough carpentry will continue.
  • Interior demolition of Westmorly and Russell Halls.
  • Steel erection within Westmorly Hall will continue.
  • Saw cutting and removal of Russell Hall slab will continue.

WORK HOURS:

  • Monday to Friday: 7am to 3:30pm
  • Saturday 11/18 – 9am to 4:30pm