Week of November 27, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 27. Please note that items in BOLD are expected to generate some noticeable noise. 


PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • The site fencing and gates along the jersey barriers on Bow Street is scheduled to be replaced.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Masonry cutting work along the west and south elevations.
  • Scaffolding installation will continue along north & west elevation of the library.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-5:00pm and Saturday it will operation from 9:00am-4:30pm.
  • Dewatering set up will continue at Russell Hall.
  • Concrete operations will mobilize.
    • Plan concrete deliveries with a pump truck is scheduled for late next week.

INTERIOR ACTIVITIES:

  • Interior rough carpentry will continue.
  • Interior demolition of Westmorly and Russell Halls.
  • Steel erection within Westmorly Hall will continue.
  • Saw cutting and removal of Russell Hall slab and Westmorly Hall slab will continue.

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 12/2- 9:00am to 4:30pm