The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 18th. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
- Trucking of soils and concrete will continue next week from Gate 2 on Bow Street.
- Eversource will continue working on the gas line at the Bow and Arrow Intersection.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Masonry cutting work along the north, west, and south elevations.
- Scaffolding installation will continue on the east elevation.
- Installation of manhole structures will continue at the East Terrace.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-5:00pm and Saturday it will operation from 9:00am-4:30pm.
- Temporary roof install will finish for Westmorly Hall.
- A crane is planned to place steel on the second and third floor out of the back parking lot on from Tuesday to Thursday.
- A vacuum truck scheduled for Monday 12/18 in the back parking lot.
- Operations will start at 7:30am.
INTERIOR ACTIVITIES:
- Interior rough carpentry will continue.
- Interior demolition of Westmorly and Russell Halls.
- Steel erection within Westmorly Hall will continue.
- Spray foam and drywall operations will continue at Westmorly Hall.
- Scaffolding for the lightwell will begin.
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm
- Saturday 12/23 – 9:00am to 4:30pm