Week of December 18, 2023

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of December 18th. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Trucking of soils and concrete will continue next week from Gate 2 on Bow Street.
  • Eversource will continue working on the gas line at the Bow and Arrow Intersection.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Masonry cutting work along the north, west, and south elevations.
  • Scaffolding installation will continue on the east elevation.
  • Installation of manhole structures will continue at the East Terrace.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-5:00pm and Saturday it will operation from 9:00am-4:30pm.
  • Temporary roof install will finish for Westmorly Hall.
  • A crane is planned to place steel on the second and third floor out of the back parking lot on from Tuesday to Thursday.
  • A vacuum truck scheduled for Monday 12/18 in the back parking lot.
    • Operations will start at 7:30am.

INTERIOR ACTIVITIES:

  • Interior rough carpentry will continue.
  • Interior demolition of Westmorly and Russell Halls.
  • Steel erection within Westmorly Hall will continue.
  • Spray foam and drywall operations will continue at Westmorly Hall. 
  • Scaffolding for the lightwell will begin.

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 12/23 – 9:00am to 4:30pm