The following summarizes the work planned on the Adams House Phase 3 renovation for the week of February 19th. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Trucking of soils and concrete will continue next week from Bow Street Gate 2.
- Concrete pump truck is scheduled to be on site Wednesday.
- A crane to support roofing work is scheduled for next Tuesday and Friday.
- A crane is scheduled to lift structural steel from Bow Street onto Russell Hall this Saturday, 2/17.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Cutting along the East and South of Westmorly Hall.
- A roofing contractor will continue abatement and demolition of the slate roof on Russell Hall.
- A crane is scheduled for to remove demolition debris from the back parking lot.
- Delivery of ductwork materials is scheduled to be delivered at Gate A off of Bow Street next Tuesday.
- Scaffolding for Russell Hall’s chimney re-building will begin.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-3:30pm and Monday/Saturday it will be in operation from 9:00am-4:30pm.
INTERIOR ACTIVITIES:
- Interior wood framing will continue in Westmorly Hall.
- Interior demolition of concrete in Russell Hall.
- Demolition of Westmorly Hall ground level slab will continue.
- Drywall and framing will continue within Westmorly Hall.
- Excavations within Russell Hall basement will continue.
- Excavations for under slab utilities within Westmorly Hall will continue.
- Shoring of existing structure in Westmorly Hall for new elevator will continue.
- Rebar and concrete work is ongoing.
- Mechanical contractors will continue with installation of new systems within Westmorly Hall.
WORK HOURS:
- Monday 2/19 – Site Closed – Presidents Day
- Tuesday to Friday: 7:00am to 3:30pm
- Saturday 2/24 – 9:00am to 4:30pm