Week of March 4, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of Marth 4th. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Trucking of soils and concrete will continue next week from Bow Street Gate 2.
  • Concrete pump truck is scheduled for next Monday in the rear parking lot.
  • There will be no work in the public way on Tuesday, March 5th, due to election polls being open.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Cutting along the East and South of Westmorly Hall.
  • A roofing contractor will continue abatement and demolition of slate roof on the Library.
  • Scaffolding for Russell Hall chimney re-build will continue.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm and Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly Hall.
  • Drywall and framing will continue within Westmorly Hall.
  • Excavation within Russell Hall’s basement will continue.
  • Excavation for under slab utilities within Westmorly Hall will continue.
  • Excavations for new footings will continue in Westmorly Hall North.
  • Excavations for new Elevator #1 in Westmorly Hall will continue.
  • Rebar & concrete work is ongoing.
  • A mechanical contractors will continue with installation of new systems within Westmorly Hall.
  • Spray foam installation is scheduled for Tuesday.  

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 3/9 – 9:00am to 4:30pm